In January 2015, Abr Projects Ltd successfully carried out our first project for Value Retail at Bicester Village. Works consisted of completely stripping back the existing units to a bone-shell, along with reconfiguring and expanding the existing unit’s internal foot print.
We constructed a new 1,000 sqft steel structural extension, on 3 metre bored piles. This was enhanced by the traditionally-themed, external Bicester cladding. The works were undertaken and successfully completed over a 17-week period. From this, we have carried out numerous other projects for value retail at Bicester Village and still continue to work with them to this day.
Bicester Village, Oxford
‘Rip out’ reconfigured with a new build extension
AB Rodgers
"We have worked with Abr for many years now and have always found them to be very trustworthy, organised, reliable and budget savvy."